Skip to content

Machine Hourly Rate Worksheet

Build a plant-defined press hourly rate from annual ownership cost, chargeable hours, and added hourly costs.

Example starting values are prefilled to demonstrate the calculation. Replace them with your measured, quoted, or job-specific inputs before relying on a result.

Inputs

Inputs

Range: at least 0 USD/year

Enter the annualized ownership-cost amount included in your internal rate policy. Exclude costs entered in the hourly field below to avoid double counting.

Range: at least 0.001 h/year

Annual chargeable/productive hours used to spread the annual ownership cost. This is not automatically 24 × 365; use your plant's scheduled-time convention. Must be greater than zero.

Range: at least 0 USD/h

Enter additional included cost per chargeable hour, such as categories in your internal rate policy. Keep items already included in annual ownership cost out of this field.

Result

Annual ownership allocation (USD/h)
30.000
Machine Hourly Rate Worksheet (USD/h)
50.000
Rate assumptions and limits
The ownership component spreads the entered annual amount over the entered planned productive hours, then adds the separate hourly amount. The result depends entirely on these user-defined accounting and scheduling assumptions; it is not a standard machine rate and does not establish quoted cost per part.